Voyager System Test-Load Adminstration Setup

Last Updated: December 12, 1997

Order of Setup:

Systems-administration table setup is centred around these major data-conversion events for the full-test load: Staff involved in entry should record start and stop times for entry so timing for each element is established

Pre-Bibliographic-Holdings Load Activity


Post-Bibliographic-Holdings Load Activity

This could commence as soon as Monday, December 15.

8:30 am

8:45 9:00-12:00 Remainder of the day allocated to Data Evaluation ?

Pre-Patron Load Activity


Post-Patron, Pre-Charge-transaction Activity

This could commence Tuesday, December 16 at 8:30am, but whenever the patron files are finished loading....

8:30

8:45

TUG- Circ Group begins entry of Circ Sys Admin.
The order of entry below is recommended. This is by far the largest section of entry; it may run for more than 1 day.

Evaluation online of the Patron Load can begin. Allocate 4 hours?

Post-Charges Load



 

Post-Vendor Load Activity: TUG ACQ

This could begin Wednesday, December 17.

8:30am

8:45-12:00?